Project background: To relocate and reconstruct four 110kV power lines in an effort to push forward the development in the east area of the high-speed railway station in Wuzhong.
Supply of products:60 sets of 64/110kV cable welding heads were completed. Cable sheath restoration process was used to achieve joint-free connection.